This page provides up-to-date information on road closures and detours related to ECUA maintenance and construction projects. Any active or upcoming closures will be listed below.

Phase 2 of the Pensacola Beach Reclaimed Water Main Project

The Emerald Coast Utilities Authority (ECUA) has begun Phase 2 of the Pensacola Beach Reclaimed Water Main Project, a $4.5 million effort to expand the reclaimed and potable water systems across Pensacola Beach. Construction began September 22, 2025, and will continue through March 2026, enhancing water sustainability and conservation in the area. Work will include installing new reclaimed and potable water mains along Via de Luna and Pensacola Beach Road, with phased lane and sidewalk closures to ensure safety.

For project updates and traffic advisories, visit www.ecua.fl.gov/advisories.

Road & Sidewalk Impacts:

Late September–October (Alvin’s Island to Quietwater Beach Rd. Intersection)

  • North sidewalk of Via de Luna closed in 500-ft sections.
  • Outside lane closures in same sections; pedestrians detoured to south sidewalk.
     

October–December (Quietwater Beach Rd. → ECUA water tanks)

  • Center turn lane work on Pensacola Beach Rd.
  • Inside lanes closed in 500-ft segments; temporary Ft. Pickens Rd. left-turn lane closure.
  • HDD rig stationed near Twice the Ice.
     

November–February (Sand Shaker to ECUA Water Tanks):

  • Two road crossings will be cut—near The Veranda and just north of Twice the Ice.
  • Lane diversions will be required as crews progress from Sand Shaker to the tanks.
     

February (Restoration):

  • Temporary asphalt and final paving; brief lane closures for restoration.